Victoria, BC– Three qualified teams have been shortlisted to participate in the next stage of the competitive selection process to design, build, partially finance, operate and maintain the Residuals Treatment Facility over a 20-year term for the Wastewater Treatment Project.

Residual solids from the McLoughlin Point Wastewater Treatment Plant will be piped to the Residuals Treatment Facility at Hartland Landfill, where they will be treated and turned into what are known as "Class A" biosolids. These biosolids are a high quality by-product safe for further use.

Seven submissions were received in response to the Request for Qualifications (RFQ) which closed on February 9, 2017. The following three teams have been selected to move forward to the Request for Proposals stage:

Harbour Resource Partners

  • AECOM Capital Inc.
  • AECOM Canada Ltd
  • Graham Capital Partners LP
  • Graham Infrastructure LP
  • SUEZ Canada Inc.
  • SUEZ Water Environmental Services Canada LP

Hartland Biosolids Partners

  • Acciona Agua, S.A..
  • Acciona Infrastructure Canada Inc.
  • Axium Intrastructure Inc.
  • Brookfield Financial Securities LP

Hartland Resource Management Group

  • Bird Capital Limited Partnership
  • Bird Design-Build Construction Inc.
  • Maple Reinders Constructors Ltd.
  • Maple Reinders PPP Ltd
  • Synagro Technologies Inc.

Proponents will submit their technical proposals by early fall and the Wastewater Treatment Project Team expects to execute a contract and begin construction in early 2018. The Residuals Treatment Facility will be complete in late 2020.

The Residuals Treatment Facility is being funded by P3 Canada, the Government of British Columbia and the CRD.

As we get closer to construction of this segment of the Project, a robust community and engagement plan will ensure the surrounding communities have advance notice of construction activity and an opportunity to engage with the Project team. Broad outreach to stakeholders will include residents, businesses, schools, day cares, recreational groups, transportation providers, tourism groups and other organizations. Communications tools will include: project information line phone number, email, social media, website, community updates, construction bulletins, traffic media updates, door-to-door advisories where appropriate, and community information meetings.

About the Wastewater Treatment Project

The Wastewater Treatment Project will provide tertiary treatment for wastewater from the core area municipalities of Victoria, Esquimalt, Saanich, Oak Bay, View Royal, Langford and Colwood, and the Esquimalt and Songhees Nations. The Wastewater Treatment Project, to be completed by the end of 2020, consists of the McLoughlin Point Wastewater Treatment Plant, the Residuals Treatment Facility at Hartland Landfill, and the conveyance system that will carry wastewater from across the core area to the treatment plant, and residual solids to the Residuals Treatment Facility. For more information, please visit www.crd.bc.ca/project/wastewater-treatment-project.