Project Type Health Care
Project Status Construction
Project Area Victoria
Estimated Cost $86,000,000

Description

The Summit at Quadra Village is a 320-unit complex residential and dementia care facility where residents will receive 24-hour care and support. The Summit will replace the aging Oak Bay Lodge (243 residents) and Mt. Tolmie Hospital (77 residents) facilities, two buildings no longer suitable for residential care.

The Summit will be a state-of-the-art residential and dementia care facility that will last for generations. The Capital Region Hospital District (CRHD) has designed and is building The Summit on behalf of Island Health. The land and future building will be owned by the CRHD and Island Health will provide the residential care services upon completion of the project, which is anticipated at the end of 2019.

Construction Updates

With Summit on schedule to complete at the end of 2019, an average of 120 trades are on site daily. This time last year, progress was most visible in the NW Quadrant with the pouring of the concrete structure and exterior steel stud framing. A year later, from many angles, the building exterior is almost complete and trades have moved inside to commence interior finishing. Inside The Summit, many projects are in progress or have been completed, starting with the NW Quadrant, then moving to the SW, SE and NE Quadrants: These include:

  • T-bar installations in resident rooms, to support the moving of patients.
  • Drywall and painting of all residents rooms.
  • Shower wall installation in resident rooms.
  • Main electrical room completed.
  • Elevator wall construction completed.
  • Underground electrical conduits in place and encased in concrete.
  • Brick veneering of stairwells.
  • Tie in to the storm sewer connection at Hillside.
  • Installation of utilities duct in the lane way.

In the background, the procurement of fixtures, furnishings and equipment by Island Health has commenced, with delivery schedules relative to completion of the different phases of the project. More than 99% of trades contracts are now awarded, with the remaining contracts including signage and fencing to be procured in coming weeks.

Work on site will continue between the hours of 7am - 7pm, except Sundays and holidays. The Capital Regional Hospital District thanks the neighbourhood for its continued patience during construction.

Images

  • washroom-epoxy-floor012019
    January 2019 - Resident Room Washroom Epoxy Floor - Click to view full size image
  • courtyard-sequadrant012019
    January 2019 - Courtyard View from SE Quadrant - Click to view full size image
  • March 2018 - Steel Stud Installation
    March 2018 - Steel Stud Installation - Click to view full size image
  • May 2018 -NW Interior
    May 2018 -NW Interior - Click to view full size image
  • may2019-1
    May 2019 - Click to view full size image
  • mechanicalroom-coating012019
    January 2019 - Rooftop Mechanical Room Traffic Coating Application - Click to view full size image
  • may2019-2
    May 2019 - Click to view full size image
  • rooftop-conduit112018
    November 2018 - Rooftop Conduit Work - Click to view full size image
  • March 2018
    March 2018 - Click to view full size image
  • may2019-5
    May 2019 - Click to view full size image
  • May 2018 - NW Quadrant
    May 2018 - NW Quadrant - Click to view full size image
  • March 2018 - Parkade
    March 2018 - Parkade - Click to view full size image
  • may2019-8
    May 2019 - Click to view full size image
  • masonry112018
    November 2018 - Masonry Work - Click to view full size image
  • May 2018 - Hillside View
    May 2018 - Hillside View - Click to view full size image
  • Jan 2018 - Suspended Slab Pour
    Jan 2018 - Suspended Slab Pour - Click to view full size image
  • March 2018 - NW Floor 3
    March 2018 - NW Floor 3 - Click to view full size image
  • loadingdock-levellers012019
    January 2019 - Loading Dock Levellers - Click to view full size image
  • may2019-7
    May 2019 - Click to view full size image
  • Jan 2018
    Jan 2018 - Click to view full size image
  • may2019-3
    May 2019 - Click to view full size image
  • groundlevel-work112018
    November 2018 - Ground Level Work Area - Click to view full size image
  • may2019-9
    May 2019 - Click to view full size image
  • may2019-4
    May 2019 - Click to view full size image
  • may2019-6
    May 2019 - Click to view full size image
  • courtyard-nwquadrant112018
    November 2018 - Courtyard from NW Quadrant - Click to view full size image
  • May 2018
    May 2018 - Click to view full size image
  • january302019
    January 30, 2019 - Click to view full size image
  • IMG_3795
    May 2018 - Click to view full size image

Receive email updates for The Summit

Subscribe

Additional Information

Contact Us

Email us to share your feedback on the Summit project.

Kevin Lorette
Project Director - The Summit
General Manager
Planning & Protective Services
Capital Regional District
Tel: 250.360.3285
Email

David Wilkinson, Architect AIBC MRAIC
Consulting Project Manager
The Summit - Residential Care Project
Tel: 250.360.3656
Email