Project Type Water
Project Status Design
Project Area North Saanich
Estimated Cost $9,800,000
Estimated Start Date 01-Aug-2023
Estimated End Date 31-Mar-2026
Contracted To / Performed By Jacobs Consultancy Canada (design)

Description

Work is planned to replace approximately 1.9km of 762mm concrete pipe on Water Supply Main 4, from the Intersection of Central Saanich Road and Mount Newton Cross Road to the crossing of Highway 17.

The CRD secured a $6-million grant through the UBCM Strategic Priorities Fund to assist with this project.

Receive email updates for Transmission Main Replacement - Mount Newton X Road

Subscribe

Contact Us

Adrian Wardle, Project Engineer
Email
250.474.9521