Project Type Water
Project Status Construction
Project Area Colwood
Estimated Cost $3,000,000
Estimated Start Date 03-Jan-2022
Estimated End Date 31-Dec-2022
Estimated Duration 1 year
Contracted To / Performed By Consultant: Colquitz Engineering, Contractor: CRD Operations

Description

Replacement of asbestos cement pipe based upon risk of failure. The 2022 year's planned section replacements include:

Colwood: Goldfinch Road, Lagoon Road, Milburn Drive
Sooke: Dufour Road, Possession Point, Richview Road, Whiffin Spit Road

Receive email updates for AC Pipe Replacement Program

Subscribe

Contact Us

Dale Puskas, Manager, Capital Projects
Email
250.474.9648