Project Type |
Water |
Project Status |
Construction |
Project Area |
Colwood |
Estimated Cost |
$3,000,000 |
Estimated Start Date |
03-Jan-2022 |
Estimated End Date |
31-Dec-2022 |
Estimated Duration |
1 year |
Contracted To / Performed By |
Consultant: Colquitz Engineering, Contractor: CRD Operations |
Description
Replacement of asbestos cement pipe based upon risk of failure. The 2022 year's planned section replacements include:
Colwood: Goldfinch Road, Lagoon Road, Milburn Drive
Sooke: Dufour Road, Possession Point, Richview Road, Whiffin Spit Road