Project Type |
Water |
Project Status |
Construction |
Project Area |
Sooke |
Estimated Cost |
$1,675,000 |
Estimated Start Date |
01-Feb-2022 |
Estimated End Date |
23-Dec-2022 |
Estimated Duration |
8 months |
Contracted To / Performed By |
Coast Utility Contracting Ltd. |
Description
Installation of a new glass-fused bolted steel tank with a proposed capacity of 1,355 cubic meters. The tank will provide domestic and fire flow water storage to the existing and future phases on the Sun River Estates development. The construction has been awarded in February 2022 with anticipated construction completion by October 2022, provided material is delivered in as anticipated.
Material delivery delays have resulted in a new target completion date in December 2022.