Project Type Water
Project Status Construction
Project Area North Saanich
Estimated Cost $3,400,000
Estimated Start Date 05-Sep-2017
Estimated End Date 01-Apr-2018
Estimated Duration 7 months
Contracted To / Performed By Parsons, CRD Infrastructure Operations

Description

The District of North Saanich is supplied from Cloake Hill Reservoir which receives water through Deep Cove Pump Station. The existing 250mm diameter Permastran water main from Deep Cove Pump Station to Cloake Hill Reservoir was constructed in 1981/82. The pipe is under capacity as well permastran is an inferior material type and subject to premature failure. The existing Permastran water main is being replaced with a new 400mm diameter Ductile Iron water main.

The CRD will complete final connections of the newly constructed water main over the following dates:

  • March 26 to March 29, 2018
  • April 3, 2018

Any disruption to the municipal water system will be communicated to residents directly from the District of North Saanich.

Receive email updates for Deep Cove Water Main Upgrade

Subscribe

Contact Us

For more information, please contact:

Shayne Irg, Project Engineer
Tel: 250.474.9661
Email

Rob Binks, Field Supervisor
Tel: 250.883.0598