Project Type Water
Project Status Construction
Project Area Southern Gulf Islands
Estimated Cost $1,445,000
Estimated Start Date 31-Dec-2020
Estimated End Date 31-Oct-2022
Estimated Duration 2 Years
Contracted To / Performed By Pacific Industrial Marine

Description

The project consists of construction of a 15 parking stall and pit toilet facility and a new approach and dock facility in Horton Bay on Mayne Island. The onshore works consisting of the parking lot and pit toilet were completed in June 2021 by Luxton Construction.

The November 15, 2021 storm event caused considerable damage to the parking lot and retaining wall, inhibiting scheduled approach and dock construction. The CRD is working with Pacific Industrial Marine to finalize remediation cost and schedule the repair works.

The current schedule for the approach and dock construction is for the summer construction Fisheries window which typically starts July 15 and ends September 30, 2022.

Whats New

Last updated March 11

  • The Description section has been updated

Receive email updates for Anson Road Dock Facility

Subscribe

Additional Information

Contact Us

Dale Puskas, Manager, Capital Projects
Email
250.474.9648