• Clover Point Pump Station Proponents Shortlisted

    May 25, 2017
    Victoria, BC–- The Wastewater Treatment Project has issued a Request for Proposals to three qualified proponents as part of the competitive selection process for the contract to design and build the expanded Clover Point Pump Station.
    Full story
  • Request for Qualifications released for the Macaulay Point Pump Station and Forcemain

    May 24, 2017
    Victoria, BC–- The Wastewater Treatment Project has issued a Request for Qualifications (RFQ) inviting interested contractors to submit their qualifications to design and build the Macaulay Point Pump Station and Forcemain.
    Full story
  • Residuals Treatment Facility Proponents Shortlisted for the Wastewater Treatment Project

    Apr 10, 2017
    Information Bulletin: Three qualified teams have been shortlisted to participate in the next stage of the competitive selection process to design, build, partially finance, operate and maintain the Residuals Treatment Facility over a 20-year term for the Wastewater Treatment Project.
    Full story
  • McLoughlin Point Wastewater Treatment Plant Contract Awarded

    Apr 05, 2017
    Information Bulletin: The first construction contract for the Wastewater Treatment Project has been awarded.
    Full story
  • Construction starting on Capital Regional District’s Wastewater Treatment Project

    Mar 16, 2017
    Full story
  • Geotechnical Work Scheduled for McLoughlin Point

    Jan 06, 2017
    Information Bulletin: The Core Area Wastewater Treatment Project will begin to gather additional information about the subsurface conditions at McLoughlin Point for the Wastewater Treatment Plant.
    Full story
  • Project Board Releases Request for Qualifications for Residuals Treatment Facility

    Dec 05, 2016
    Information Bulletin: Today the Core Area Wastewater Treatment Project Board (Project Board) released a Request for Qualifications (RFQ) for the Residuals Treatment Facility at Hartland landfill, one of the major components of the Core Area Wastewater Treatment Project.
    Full story
  • CRD Board Approves Independent Project Board Recommendation for Core Area Wastewater Treatment

    Sep 14, 2016
    Media Release: The Capital Regional District (CRD) Board approved the recommendations put forward by the Core Area Wastewater Treatment Project Board (CAWTPB) which will form Amendment 11 of the Core Area Liquid Waste Management Plan.
    Full story
  • Core Area Wastewater Treatment Project Board Releases Final Report

    Sep 07, 2016
    Full story
  • CRD Board Announces Membership of Core Area Wastewater Treatment Project Board

    Jun 09, 2016
    The CRD Board has announced the appointments that will make up the Core Area Wastewater Treatment Project Board.
    Full story
  • CRD Approves Terms of Reference for Wastewater Project Board

    May 25, 2016
    Media Release: At the Capital Regional District (CRD) Board meeting today, directors approved Terms of Reference for the new Core Area Wastewater Project Board.
    Full story
  • CRD Adopts Project Board Approach to Core Area Wastewater Project

    May 11, 2016
    After hearing a presentation from Minister Peter Fassbender, at the CRD Board meeting, the CRD Board decided to adopt a standard project management framework approach that will allow for the project to move into the Planning Phase and meet the federal 2020 deadline.
    Full story
  • Federal Government Confirms CRD Risk Designation for Wastewater Treatment by 2020

    Apr 18, 2016
    Information Bulletin: The Federal Government confirmed the CRD’s risk designation status in a letter to the Chair of the Core Area Liquid Waste Management Committee (CALWMC).
    Full story
  • Approval of Federal PPP Canada Funding Extension

    Mar 30, 2016
    Victoria-The CRD's CAO, Robert Lapham, has signed an extension of the conditional agreement with PPP Canada that will allow for a six-month funding extension while the committee continues to make progress on planning for enhanced wastewater treatment for the Core Area.
    Full story
  • Province Supports Extension Request for Wastewater Planning

    Mar 23, 2016
    Victoria, BC- In a letter to the Federal Minister of infrastructure and Communities, the province has expressed its support for an extension to the P3 Canada funding agreement which currently expires on March 31, 2016.
    Full story
  • CALWMC Selects Two-Plant Treatment Option; Will Work with Province in Planning Phase

    Mar 09, 2016
    Media Release: The Core Area Liquid Waste Management Committee (CALWMC) selected a two-plant treatment option as a base case to form a conditional amendment to the 2010 Liquid Waste Management Plan (LWMP).
    Full story
  • Sewage train is headed safely for the station-Opinion Article by Director Helps

    Feb 05, 2016
    Opinion Article: Last week, editorial writers at the Times Colonist stated with regard to the sewage project: “not even the most confirmed skeptic could have seen the train wreck now emerging.”....That is, until we look at the facts and the process currently underway.
    Full story
  • Core Area Wastewater Consultation Launches with Online Survey and Consultation Opportunities

    Jan 26, 2016
    Media Release: The Chairs of the Eastside and Westside Wastewater Treatment and Resource Recovery Select Committees (Eastside and Westside Select Committees) officially launched an online survey today as part of the public consultation on potential wastewater treatment options.
    Full story
  • CALWMC Seeking Public Input on Approaches to Wastewater Treatment

    Jan 14, 2016
    Media Release: The Core Area Liquid Waste Management Committee (CALWMC) voted to begin consultation on a number of approaches to wastewater treatment in the Core Area.
    Full story
  • Cost Estimates, Environmental Benefits and Sites for Five Core Area Wastewater Treatment Options Released Today

    Dec 04, 2015
    Information Bulletin: Today, the CRD released a report with new information relating to the Core Area wastewater treatment project.
    Full story