• CRD Board Approves Limited Beneficial Use of Biosolids at Hartland Landfill

    Feb 12, 2020
    The CRD Board has approved a motion to allow a portion of biosolids produced at the Residuals Treatment Facility to be used at Hartland Landfill.
    Full story
  • Final Contract Awarded for the Wastewater Treatment Project

    Jan 09, 2020
    The CRD has awarded a $6.8-million contract to Jacob Bros Construction to construct the Trent Forcemain.
    Full story
  • Arbutus Attenuation Tank Contract Awarded

    May 10, 2019
    The CRD has awarded a $17.7-million contract to NAC Constructors Ltd to construct the Arbutus Attenuation Tank.
    Full story
  • CRD Seeks Feedback on Biosolids Beneficial Use Strategy

    Apr 29, 2019
    The Capital Regional District (CRD) is planning to procure services for the beneficial use of the biosolids produced at its Residuals Treatment Facility.
    Full story
  • Residual Solids Pump Stations Contract Awarded

    Apr 26, 2019
    The CRD has awarded a $15.9-million contract to Knappett Projects Inc. to construct three pump stations and bridge crossings along the Residual Solids Conveyance Line for the Wastewater Treatment Project.
    Full story
  • Wastewater Treatment Project Board Requests Additional Funding

    Apr 12, 2019
    The Wastewater Treatment Project has made significant progress with the majority of the Project under construction. To complete the Project by the regulatory deadline of December 31, 2020, the Project Board is seeking approval from the CRD Board for an additional $10 million of funding.
    Full story
  • Statement Regarding Grange Road

    Dec 13, 2018
    The Wastewater Treatment Project has responded to residents’ concerns about the loss of trees and has found a way to construct the Residual Solids Conveyance Line that doesn’t require the removal of any trees on Grange Road.
    Full story
  • Residual Solids Conveyance Line Contract Awarded

    Nov 07, 2018
    The Capital Regional District (CRD) has awarded a $29-million contract to Don Mann Excavating Ltd. to construct the Residual Solids Conveyance Line (RSCL).
    Full story
  • Ganges Wastewater Treatment Plant Upgrades Ahead of Schedule

    Sep 26, 2018
    A recent staff report to the Ganges Sewer Local Services Commission on Salt Spring Island confirms that the Ganges Wastewater Infrastructure Renewal Project is progressing well and is within budget and ahead of schedule.
    Full story
  • Clover Forcemain Contract Awarded

    Sep 21, 2018
    The Capital Regional District (CRD) has awarded a $30.9-million contract to Windley Contracting Ltd. to construct the Clover Forcemain.
    Full story
  • Temporary Wastewater Bypass for Ganges Wastewater Treatment Plant Upgrade on Salt Spring Island

    Aug 09, 2018
    The CRD is currently upgrading the wastewater treatment plant in Ganges Village on Salt Spring Island and in order to complete the work a wastewater bypass is required between August 16 and August 28, 2018.
    Full story
  • Residuals Treatment Facility Contract Award

    Feb 06, 2018
    The Capital Regional District (CRD) has entered into a contract with Hartland Resource Management Group to design, build, finance, operate and maintain the Residuals Treatment Facility over a 20-year term.
    Full story
  • Macaulay Point Pump Station and Forcemain Contractor Selected

    Feb 01, 2018
    The contractor for the Macaulay Point Pump Station and Forcemain has been selected and is Kenaidan Contracting Ltd.
    Full story
  • CRD Board Appoints New Chair of Core Area Wastewater Treatment Project Board

    Dec 15, 2017
    The CRD Board has appointed Don Fairbairn as Chair of the Core Area Wastewater Treatment Project Board. Don Fairbairn previously served as Project Board Vice-Chair.
    Full story
  • Residuals Treatment Facility Preferred Proponent Selected

    Dec 12, 2017
    Victoria, BC–- Hartland Resource Management Group has been selected as the preferred proponent to design, build, partially finance, operate and maintain the Residuals Treatment Facility over a 20-year term for the Wastewater Treatment Project.
    Full story
  • Clover Point Pump Station Contractor Selected

    Nov 22, 2017
    Victoria, BC– The contractor for the Clover Point Pump Station has been selected and is Kenaidan Contracting Ltd.
    Full story
  • Macaulay Point Pump Station and Forcemain Proponents Shortlisted

    Aug 25, 2017
    The Wastewater Treatment Project has issued a Request for Proposals (RFP) to three qualified proponents as part of the competitive selection process for the contract to design and build the Macaulay Point Pump Station and Forcemain.
    Full story
  • Clover Point Pump Station Proponents Shortlisted

    May 25, 2017
    Victoria, BC–- The Wastewater Treatment Project has issued a Request for Proposals to three qualified proponents as part of the competitive selection process for the contract to design and build the expanded Clover Point Pump Station.
    Full story
  • Request for Qualifications released for the Macaulay Point Pump Station and Forcemain

    May 24, 2017
    Victoria, BC–- The Wastewater Treatment Project has issued a Request for Qualifications (RFQ) inviting interested contractors to submit their qualifications to design and build the Macaulay Point Pump Station and Forcemain.
    Full story
  • Residuals Treatment Facility Proponents Shortlisted for the Wastewater Treatment Project

    Apr 10, 2017
    Information Bulletin: Three qualified teams have been shortlisted to participate in the next stage of the competitive selection process to design, build, partially finance, operate and maintain the Residuals Treatment Facility over a 20-year term for the Wastewater Treatment Project.
    Full story