Project Type Water
Project Status Design
Project Area Highlands
Estimated Cost $1,200,000
Estimated Start Date 15-Aug-2017
Estimated End Date 31-Mar-2018
Estimated Duration 7.5 months
Contracted To / Performed By Design by Stantec Consulting Ltd., Construction by CRD Infrastructure Operations

Description

The CRD is extending approximately 575 meter of new 400mm diameter Ductile Iron restrained water main. The water main is to service industrial lands along Millstream Road as well as the Bear Mountain development.

Receive email updates for Millstream Water Main

Subscribe

Contact Us

Shayne Irg, P.Eng., Project Engineer
CRD Integrated Water Services
250.474.9661
Email

Rob Binks, Field Supervisor
CRD Integrated Water Services
250.883.0598