Project Type Water
Project Status Construction
Project Area Metchosin
Estimated Cost $1,000,000
Estimated Start Date 04-Feb-2019
Estimated End Date 31-May-2019
Estimated Duration 4 Months
Contracted To / Performed By CRD Infrastructure Operations

Description

The CRD is replacing approximately 1130m of existing AC watermain with a new 300mm Ductile Iron watermain along Metchosin Road from the Green Acres Golf Course to ~200m east of Brotherstone Road. The existing watermain was installed in 1960 and is nearing the end of its lifecycle.

Receive email updates for Metchosin Road Water Main Upgrade

Subscribe

Additional Information

Gary Jay
CRD Integrated Water Services
Infrastructure Operations
250.883.0611