Project Type Liquid Waste
Project Status Design
Project Area Salt Spring Island
Estimated Cost $195,000
Estimated Start Date 03-Dec-2018
Estimated End Date 05-Apr-2019
Estimated Duration 4 months

Description

Maliview sewer service requires replacement of the land portion of the sewer treatment plant outfall pipe and repairs to the gravity sewer collection. The outfall from the rotating biological contactor (RBC) unit to the marine portion of the outfall has deteriorated significantly and is at risk of repeated failures. Replacement of the land portion of the outfall will reduce unscheduled/unplanned repairs.

The Maliview sewer outfall portion of the works includes replacing approximately 10m of the outfall with a new section of pipe. The Maliview sewer collection system portion of the works includes spot repairs of Inflow and Infiltration (I&I) leaks along the approximately 1.1 km long sewer main.

Construction is scheduled to start on Monday, February 25 with a completion date of April 5.

This project was made possible with the assistance of Federal Gas Tax Funding, with $195,000 allocated by the CRD as part of the Community Works Fund for the Salt Spring Island electoral area.

Whats New

Last updated February 15

  • Estimated End Date and Duration has been updated
  • Description has been updated