Stormwater Rehabilitation Unit 3
This stormwater unit is underground; it was a public municipality retrofit completed in 2006.
Rainwater Management Techniques
Underground Cleansing
A concrete vault with aluminum swirl chamber was built in place, in line with underground storm drains. It has an 8 hectare catchment area.
Cost & Funding
$12,000, equally shared between local, provincial and federal governments via an infrastructure grant.
Project Team
City of Victoria Storm Water Quality Officer, Water and Environment Engineering Section.